ZINA: Create new post-associated bundle CRIA
by ZINATeamZINA Workflow Management: CRIA - Create new post-associated bundle

CR workflow using IPM and CRIA.
• CRIA stands for Change Request Innovative Automation. It’s a tool developed by Business Operations team for Latin America.
• CRIA tool aims to allow automation in the approval chain for Change Requests and centralize the database with information associated with these CRs.
• CRIA acts in the process of Change Requests approval. It is still needed and mandatory the usage of IPM for all other processes associated with CRs.
• This document describes the operational procedures for end users to import CR data from IPM and the benefits of the CRIA tool usage.







In the CR Bundle menu, you will have 3 possibilities:
1. CR bundle report: View CR bundle detail report.
2. Create a pre-associated Bundle CR: In this bundle, we already know all Change Requests that must be included in the package before sending bundle request for approval. (CT TIM Brazil is the only team using this feature at this moment)
3. Create a

In the side menu, display the “CRIA Tool" options.

Select the “Create

Edit a bundle name and provide a general bundle description.

Select customer team of Bundle (only available for those allowed by Key Users) and define the type of flow to be used.

Then, complete Bundle Cost Value field in Euros and check the box if bundle should be sent for approval chain.

Complete Bundle Sales Value field in Euros and click on the “Save changes” blue button, as the image shows.

If your creation process was successful, you will see a green alert indicating that Your Bundle has been submitted successfully.